On 27 August 2026, Airports Corporation of Vietnam (ACV), together with Da Nang city authorities, announced the launch of a project to renovate and expand Terminal 1 and expand the aircraft apron (phase 1) at Da Nang International Airport. The project has a total investment of over VND 9,936 billion and aims to raise the airport’s operating capacity to 14 million passengers a year, meeting demand for about 10 million domestic and 4 million international passengers.
The project is expected to break ground in August 2027; the apron expansion is due to finish in January 2029, and the full terminal renovation by August 2029. Da Nang International Airport — built in 1940 and now 86 years old — sits only about 3 km from the city centre, seen as a major advantage for regional transport connectivity as its operating capacity nears design limits amid fast-rising visitor numbers to Da Nang.
Over VND 9,936 billion.
14 million passengers a year, about 10 million domestic and 4 million international.
Groundbreaking is expected in August 2027; the apron is due in January 2029, and the full terminal by August 2029.
Written by the association from published reporting; figures and quotes follow the sources above.

On the morning of September 3, 2026, the Standing Committee of the Da Nang Tourism Association held a working session with the Organizing Committee of DITF – Da Nang International Tourism Festival 2026 to review progress and agree on key priorities during the final preparation phase for the event.

Da Nang Tourism Association Holds Expanded Standing Committee Meeting to Accelerate Preparations for DITF – Danang International Tourism Festival 2026

From 12 to 17 August 2026 at the Da Nang Convention and Exhibition Centre, the East–West Economic Corridor International Trade, Tourism and Investment Fair – Da Nang 2026 gathers nearly 250 booths from 108 domestic and foreign businesses, six southern Lao provinces and nine diplomatic missions.